The PRINCE2 Foundation certification exam is an essential step towards becoming a certified PRINCE2 practitioner. It is a globally recognized certification that demonstrates your knowledge and understanding of the PRINCE2 methodology. By taking a PRINCE2 Foundation course and passing the exam, you can enhance your project management skills and improve your career prospects.
NEW QUESTION # 264
The application of which principle helps to define what should be included in a project?
- A. Manage by stages
- B. Defined roles and responsibilities
- C. Continued business justification
- D. Focus on products
Answer: A
Explanation:
Section: Volume B
NEW QUESTION # 265
What must be produced to meet the minimum requirements for applying the change theme?
- A. Documentation on the version of each product
- B. Details of the decisions taken on all issues
- C. Details of the status of all products being produced
- D. Documentation on the corrective action for an issue
Answer: B
Explanation:
Section: Volume B
Explanation/Reference: http://prince2.wiki/Themes#Change_Theme
NEW QUESTION # 266
Which is a benefit of using PRINCE2?
- A. Is a method specifically designed for technical projects
- B. Provides for the efficient and economic use of management time
- C. Can be used to manage both projects and programmes
- D. Includes many of the proven planning techniques, such as critical path analysis
Answer: B
NEW QUESTION # 267
According to the 'manage by exception' principle, which aspect of performance sets limits against the cost of aggregated threats?
- A. Risk
- B. Cost
- C. Scope
- D. Quality
Answer: B
Explanation:
The principle of 'manage by exception' in PRINCE2 involves setting limits on delegated authority concerning time, cost, quality, scope, risk, and benefits. Here, the aspect of performance that sets limits against the cost of aggregated threats is "Cost". This includes setting tolerances for what can be considered acceptable deviations from the plan before an issue needs to be escalated to a higher authority. Managing by exception helps in efficient use of management time and focuses on deviations that might affect the project's success.References:
(PRINCE27 Foundation Handbook, AXELOS)
NEW QUESTION # 268
Which process has the objective of confirming that acceptance criteria have been met?
- A. Managing product delivery
- B. Controlling a stage
- C. Directing a project
- D. Closing a project
Answer: D
Explanation:
In PRINCE2, the "Closing a Project" process has the objective of confirming that the project's products are acceptable and meet the established acceptance criteria. This process ensures that the project has delivered the required outputs as agreed upon, and these outputs are approved and accepted by the customer. References:
PRINCE2 Foundation Guide, "Closing a Project" section
NEW QUESTION # 269
As a minimum requirement for applying the risk theme, what must specifically be assessed?
- A. Whether a risk may cause the project to exceed its cost tolerance
- B. Whether a risk may alter the project's business justification
- C. Whether a risk may impact the underlying technical assumptions
- D. Whether a risk may affect the project-level quality tolerances
Answer: B
NEW QUESTION # 270
Identify the missing words in the following sentence.
The 'starting up a project" process is triggered when a [ ? J is available.
- A. work package
- B. stage plan
- C. project mandate
- D. project business case
Answer: C
NEW QUESTION # 271
Which is a purpose of the 'initiating a project' process?
- A. To identify the number of work packages required
- B. To establish solid foundations for a project
- C. To decide if it is worthwhile to initiate a project
- D. To decide on the project approach
Answer: B
Explanation:
Explanation
Reference http://prince2.wiki/Initiating_a_Project#Objective
NEW QUESTION # 272
What should be considered when defining the number of management stages in a project?
- A. When project support will be available
- B. When key decisions need to be made
- C. When highlight reports will be submitted
- D. When the team managers are available
Answer: B
Explanation:
Explanation
Reference https://www.prince2primer.com/prince2-management-and-technical-stages/
NEW QUESTION # 273
Which process ensures focus on the delivery of a stage's products and avoids uncontrolled change?
- A. Starting up a project
- B. Controlling a stage
- C. Managing a stage boundary
- D. Directing a project
Answer: B
Explanation:
Section: Volume B
Explanation/Reference:
Reference https://www.greycampus.com/opencampus/prince-2-foundation/introduction-on-controlling-a-stage- process-in-prince2
NEW QUESTION # 274
Identify the missing words in the following sentence.
The 'directing a project' process starts when [ ? ] and is triggered by the request to initiate a project.
- A. the 'starting up a project' process is completed
- B. the project mandate has been approved by the project board
- C. corporate, programme management or the customer have authorized a project
- D. the project board has agreed the project strategies
Answer: A
Explanation:
Explanation
Reference https://www.siliconbeachtraining.co.uk/blog/prince2-directing-project-process-dp
NEW QUESTION # 275
What product is used to maintain a record of those who have an interest in the project and their information requirements?
- A. Project Product Description
- B. Project Brief
- C. Communication Management Strategy
- D. Project Plan
Answer: C
Explanation:
The Communication Management Strategy is used in PRINCE2 to maintain a record of stakeholders who have an interest in the project and their information requirements. This document outlines how and when stakeholders will be kept informed about the project's progress and any issues that may arise. References:
PRINCE2 Foundation manual, PRINCE2 official resources
NEW QUESTION # 276
Which is the purpose of the Change theme?
- A. Assess and control uncertainty
- B. Prevent change to baselined products
- C. Establish mechanisms to monitor and compare actual achievements against those planned
- D. Identify, assess and control any potential and approved changes to baselined products
Answer: D
NEW QUESTION # 277
Which is a key decision made during the 'directing a project' process?
- A. Select and appoint the project executive
- B. Confirm that the benefits management approach addresses all expected benefits
- C. Approve the project manager role description
- D. Approve the proposed project mandate
Answer: C
Explanation:
Section: Volume B
Explanation/Reference: https://www.greycampus.com/opencampus/prince-2-practitioner/purpose-of-directing-a-project- process-in-prince2
NEW QUESTION # 278
Which statement is CORRECT about the customer and suppliers of a project in a commercial environment?
- A. Both parties must apply the same external governance to the project
- B. Each party may have their own business case for undertaking the project
- C. Management systems need to be unified for successful project delivery
- D. The risk appetite should be collaboratively set before the project starts
Answer: B
Explanation:
In a commercial environment, it is common for each party involved in a project-namely the customer and suppliers-to have their own business case. This reflects their individual motives, expected benefits, and investment rationale for undertaking the project. Each party's business case addresses their specific strategic, commercial, and operational needs.References: = PRINCE2 7 Foundation handbook and online resources
NEW QUESTION # 279
Identify the missing words in the following sentence.
The project manager [ ? ] for day-to-day management of the project.
- A. decides who is responsible
- B. and the team manager(s) are accountable
- C. and the project board are responsible
- D. has responsibility
Answer: D
Explanation:
Section: Volume B
Explanation/Reference: http://prince2.wiki/Directing_a_Project
NEW QUESTION # 280
Which PRINCE2 principle is being applied when tolerances are set to establish limits of authority and accountability?
- A. Manage by stages
- B. Defined roles and responsibilities
- C. Continued business justification
- D. Manage by exception
Answer: D
Explanation:
Section: Volume B
Explanation/Reference: http://prince2.wiki/Manage_by_exception
NEW QUESTION # 281
What process is used by the Project Board to respond to an Exception Report?
- A. Controlling a Stage
- B. Managing Product Delivery
- C. Directing a Project
- D. Managing a Stage Boundary
Answer: C
NEW QUESTION # 282
Which should be provided by corporate or programme management before the Starting up a Project process commences?
- A. Authority to initiate a project
- B. The Project Initiation Documentation
- C. Sufficient information to identify the prospective Executive
- D. A Project Brief
Answer: C
Explanation:
Section: Volume B
NEW QUESTION # 283
Which theme provides the controls to escalate any forecast beyond tolerance to the next management level?
- A. Progress
- B. Plans
- C. Quality
- D. Business Case
Answer: A
NEW QUESTION # 284
Which principle helps to ensure that all changes to the outputs are agreed?
- A. Defined roles and responsibilities
- B. Manage by exception
- C. Focus on products
- D. Learn from experience
Answer: A
NEW QUESTION # 285
Which is a benefit of using PRINCE2?
- A. Can be tailored by leaving out elements of the method for some projects
- B. Enables the management of projects as well as of 'business as usual' activities
- C. Avoids the need to involve corporate or programme management
- D. Can be applied to any type of project
Answer: D
Explanation:
Section: Volume A
NEW QUESTION # 286
What plan is created, and submitted for approval, during the Managing a Stage Boundary process?
- A. Team Plan
- B. Benefits Review Plan
- C. Project Plan
- D. Stage Plan
Answer: D
Explanation:
Section: Volume B